Gazelle Progress Tracker
From IHEWiki
Contents |
[edit]
Gazelle Major Deliverables
This section lists the major deliverables to field a complete Gazelle test management system at the Bordeaux Connectathon, April 2010.
| Feature | Projected Delivery | Eric Test | Lynn Test | Steve Test |
|---|---|---|---|---|
| Registration, User Mgmt, Systems registration, Contract Mgmt | 01-Oct-2009 | |||
| Configuration management, including certificates | 15-Oct-2009 | |||
| Static object management | 01-Nov-2009 | |||
| Final scores and result output | 15-Oct-2009 | |||
| Data entry for Test Cases. Includes conversion from Kudu. | 15-Oct-2009 | |||
| Test engine controls tests without simulators | 15-Oct-2009 | |||
| Standalone simulators to support Internet testing (A04 out, QED/PIX/or PDQ in) | 15-Oct-2009 | |||
| Integrate simulators (MIR, NIST) with test engine. | ||||
| Test engine controls tests with simulators (final product) | ||||
| QC of Connectathon tests by test authors | ||||
| Implementation of more simulators to support Bordeaux | 16-Nov-2009 |
[edit]
2009
[edit]
26-Oct-2009
Delivered Features (12-Oct-2009 thru 26-Oct-2009)
| Who | Delivered | Next Step |
|---|---|---|
| INRIA | ||
| MIR | QED client/server using web services | Install in MIR DMZ this week or next. |
Planned Features (28-Oct-2009 thru 9-Nov-2009)
| Who | Projected Deliverable for 28-Sep-2009 | Next Step |
|---|---|---|
| INRIA | ||
| MIR | QED Server in MIR DMZ | |
| MIR | HL7 V2 ADT client in MIR DMZ with Web GUI | Tie in HL7 V3 ADT client |
| MIR | PIX/PDQ servers in MIR DMZ to assist with XDS.b testing | |
| MIR | Continue work on existing MESA platform for new profiles |
[edit]
28-Sep-2009
Delivered Features (14-Sep-2009 thru 28-Sep-2009)
| Who | Delivered | Next Step |
|---|---|---|
| INRIA | Port to Jboss 5 and JDK 6 : Application TM, PR, GMM and DDS are now ported to Jboss 5 and JDK 6. This is still under test and production is not using Jboss 5 for the moment. | Continue testing and developping with Jboss 5 and JDK 6. Migrate test engine to Jboss 5. 90% of the tasked is now done. We still need to fix a problem with pdf generation using jasperreports (low level task) |
| INRIA | Certificates management: Work is still in progress. Application can now generate certificate requests as well as selfed signed certificates. | Need validation with CA and extended testing. 90% of the tasked is done. We need to finish the upload of certificates generated by the CA. Deletion of certificates when deleting a system. |
| INRIA | Configuration Management | Improved of access to configuration. Needed by simulators and Test Engine. Need to add drools data for the new Integration profiles |
| INRIA | Proxy | First component of the proxy is now available : start and stop of proxy between 2 sockets. Capture of HL7 messages
|
| INRIA | Product Registry | Worked on the management part of PR. The crawler that checks the availability of the integration statements online. Improvement of the GUI and port to Jboss 5 |
| INRIA | Demographic Data Server : First version of the Demographic Data Server is available. The server allow the generation of dummy patients for testing purpose. The dummy patient have names that are realistics and addresses that make sense. The tool night build is available at the following url : http://sumo-test.irisa.fr:8080/DDS. A web service is also available that allow a request to the server to send an HL7 message to specific IP/port. | Still need to work on the following task.
Abderrazek will start on the project this week. |
[edit]
14-Sep-2009
Delivered Features (31-Aug-2009 thru 14-Sep-2009)
| Who | Delivered | Next Step |
|---|---|---|
| INRIA | Port to Jboss 5 and JDK 6 : Application TM, PR, GMM and DDS are now ported to Jboss 5 and JDK 6. This is still under test and production is not using Jboss 5 for the moment. | Continue testing and developping with Jboss 5 and JDK 6. Migrate test engine to Jboss 5. |
| INRIA | Certificates management: Work is still in progress. Application can now generate certificate requests as well as selfed signed certificates. | Need validation with CA and extended testing. |
| INRIA | Monitor Management is now available in the application. | Need testing |
| INRIA | Configuration Management | |
| INRIA | Demographic Data Server : First version of the Demographic Data Server is available. The server allow the generation of dummy patients for testing purpose. The dummy patient have names that are realistics and addresses that make sense. The tool night build is available at the following url : http://sumo-test.irisa.fr:8080/DDS. A web service is also available that allow a request to the server to send an HL7 message to specific IP/port. |
|
| MIR | Hand off design of PCC/CDA tests to Steve Moore | Steve to start writing PCC/CDA content tests |
| MIR | Have base classes for simulator actors, including command-line control program, WSDL web server control interface, server and client message processors, HL7V2 message server and client, simple HL7V2 client and server implementations | Have tied together command line interface and WSDL applications. Need to tie in Web GUI |
Planned Features (14-Sept-2009 thru 28-Sept-2009)
| Who | Projected Deliverable for 28-Sep-2009 | Next Step |
|---|---|---|
| INRIA | ||
| MIR - Miss from last time, need to deliver for 28-Sep | At least one simulator/server responding to V3 queries (QED, or PIXV3, or PDQV3). Answers read out of a fixed database with SQL entered by hand (e.g., 5 PIX patients in a database, no GUI to enter more patients). | Move that into DMZ for participant testing in Oct |
| MIR | Web GUI that allows user to enter demographics and send V2 A04 message. The purpose is to place this tool in the MIR DMZ so users can send A04 messages with patient identifiers to the NIST registry, to registries from other participants and to PIX managers / PDQ suppliers available on the Internet. | Need to tie Web GUI to Web Service functions. |
| MIR | Start writing PCC content tests | |
| MIR | Continue work on existing MESA platform for new profiles | Oct 1 delivery data for participants |
[edit]
31-Aug-2009
Delivered Features (17-Aug-2009 thru 31-Aug-2009)
| Who | Delivered | Next Step |
|---|---|---|
| INRIA | Release of ProductRegistry Version 1.0-GA | Announce it to vendor for data entry |
| MIR | Finish investigation of PCC/CDA test content | Hand off meeting 3-Sep. Work is complete |
| MIR | Have base classes for simulator actors, including command-line control program, WSDL web server control interface, server and client message processors, HL7V2 message server and client, simple HL7V2 client and server implementations | Base classes are done. |
| MIR | Bring Kudu NA 2010 online. Finish testing data entry/registration pieces | Open for registration. |
Planned Features (1-Sept-2009 thru 14-Sept-2009)
| Who | Projected Deliverable for 14-Sep-2009 | Next Step |
|---|---|---|
| INRIA | Add Synchronization of GMM to TM and PR : We need to have a mechanism to automatically broadcast changes in the Master Model to propagate changes in the models toward slave applications | |
| INRIA | Certificates management | |
| INRIA | Objects management | |
| INRIA | Migration to Jboss 5 and Java 6 | |
| MIR | At least one simulator/server responding to V3 queries (QED, or PIXV3, or PDQV3). Answers read out of a fixed database with SQL entered by hand (e.g., 5 PIX patients in a database, no GUI to enter more patients). | Move that into DMZ for participant testing in Oct |
| MIR | Web GUI that allows user to enter demographics and send V2 A04 message. The purpose is to place this tool in the MIR DMZ so users can send A04 messages with patient identifiers to the NIST registry, to registries from other participants and to PIX managers / PDQ suppliers available on the Internet. | Synchronize with INRIA demographics service. Move to DMZ for Oct testing |
| MIR | Start writing PCC content tests (MESA) | |
| MIR | Continue work on existing MESA platform for new profiles | Oct 1 delivery data for participants |
[edit]
17-Aug-2009
Delivered Features (3-Aug-2009 thru 17-Aug-2009)
| Who | Delivered | Next Step |
|---|---|---|
| MIR (Maffitt/Kelsey) | 1 week vacation | |
| INRIA (Poiseau) | 2 week vacation | |
| MIR | Investigate tooling to test content of PCC/CDA documents | Finish investigation. Hand off to Steve |
| MIR | Design basic structure for simulators / controllers | Review NIST simulators |
| MIR | Gazelle Master Model maintenance (bug fixes, no new features) | Bug fixes as necessary |
Planned Features (17-Aug-2009 thru 31-Aug-2009)
| Who | Projected Deliverable for 31-Aug-2009 | Next Step |
|---|---|---|
| MIR | Finish investigation of PCC/CDA test content | Hand off to Steve by 31-Aug |
| MIR | Have base classes for simulator actors, including command-line control program, WSDL web server control interface, server and client message processors, HL7V2 message server and client, simple HL7V2 client and server implementations | Simulators |
| MIR | Bring Kudu NA 2010 online. Finish testing data entry/registration pieces | Open registration, 28-Aug-2009 |
| INRIA | Connectathon Monitor Management : | |
| INRIA | Configuration Management :
| Check for missing configuration in the tool |
| INRIA | Created a version of Gazelle for demonstration purpose. Available at the URL : http://sumo-test.irisa.fr:8080/gazelle-demo | Add a dns entry to make it available under gazelle-demo.ihe.net and announce it. |
| INRIA | Added the possibility to start tests and grade tests. User can select test partners, test is started and test engine is invoked for handling the "choreography" of the test. |
|