Gazelle Major Deliverables

This section lists the major deliverables to field a complete Gazelle test management system at the Bordeaux Connectathon, April 2010.

Feature Projected Delivery Eric Test Lynn Test Steve Test
Registration, User Mgmt, Systems registration, Contract Mgmt 01-Oct-2009      
Configuration management, including certificates 15-Oct-2009      
Static object management 01-Nov-2009      
Final scores and result output 15-Oct-2009      
Data entry for Test Cases. Includes conversion from Kudu. 15-Oct-2009      
Test engine controls tests without simulators 15-Oct-2009      
Standalone simulators to support Internet testing (A04 out, QED/PIX/or PDQ in) 15-Oct-2009      
Integrate simulators (MIR, NIST) with test engine.        
Test engine controls tests with simulators (final product)        
QC of Connectathon tests by test authors        
Implementation of more simulators to support Bordeaux 16-Nov-2009      

2009

26-Oct-2009

Delivered Features (12-Oct-2009 thru 26-Oct-2009)

Who Delivered Next Step
INRIA    
MIR QED client/server using web services Install in MIR DMZ this week or next.

Planned Features (28-Oct-2009 thru 9-Nov-2009)

Who Projected Deliverable for 28-Sep-2009 Next Step
INRIA    
MIR QED Server in MIR DMZ  
MIR HL7 V2 ADT client in MIR DMZ with Web GUI Tie in HL7 V3 ADT client
MIR PIX/PDQ servers in MIR DMZ to assist with XDS.b testing  
MIR Continue work on existing MESA platform for new profiles  

28-Sep-2009

Delivered Features (14-Sep-2009 thru 28-Sep-2009)

Who Delivered Next Step
INRIA Port to Jboss 5 and JDK 6 : Application TM, PR, GMM and DDS are now ported to Jboss 5 and JDK 6. This is still under test and production is not using Jboss 5 for the moment. Continue testing and developping with Jboss 5 and JDK 6. Migrate test engine to Jboss 5. 90% of the tasked is now done. We still need to fix a problem with pdf generation using jasperreports (low level task)
INRIA Certificates management: Work is still in progress. Application can now generate certificate requests as well as selfed signed certificates. Need validation with CA and extended testing. 90% of the tasked is done. We need to finish the upload of certificates generated by the CA. Deletion of certificates when deleting a system.
INRIA Configuration Management Improved of access to configuration. Needed by simulators and Test Engine. Need to add drools data for the new Integration profiles
INRIA Proxy First component of the proxy is now available : start and stop of proxy between 2 sockets. Capture of HL7 messages
  • Need to capture Dicom conversation
  • Need to store data in the database.
INRIA Product Registry Worked on the management part of PR. The crawler that checks the availability of the integration statements online. Improvement of the GUI and port to Jboss 5
INRIA Demographic Data Server : First version of the Demographic Data Server is available. The server allow the generation of dummy patients for testing purpose. The dummy patient have names that are realistics and addresses that make sense. The tool night build is available at the following url : http://sumo-test.irisa.fr:8080/DDS. A web service is also available that allow a request to the server to send an HL7 message to specific IP/port. Still need to work on the following task.
  • Add a dns entry to make it available under demographic-data-server.ihe.net .
  • Add entries for japan (firstname and lastname)
  • Write documentation for end user
  • Announce it, for trial usage

Abderrazek will start on the project this week.

14-Sep-2009

Delivered Features (31-Aug-2009 thru 14-Sep-2009)

Who Delivered Next Step
INRIA Port to Jboss 5 and JDK 6 : Application TM, PR, GMM and DDS are now ported to Jboss 5 and JDK 6. This is still under test and production is not using Jboss 5 for the moment. Continue testing and developping with Jboss 5 and JDK 6. Migrate test engine to Jboss 5.
INRIA Certificates management: Work is still in progress. Application can now generate certificate requests as well as selfed signed certificates. Need validation with CA and extended testing.
INRIA Monitor Management is now available in the application. Need testing
INRIA Configuration Management
INRIA Demographic Data Server : First version of the Demographic Data Server is available. The server allow the generation of dummy patients for testing purpose. The dummy patient have names that are realistics and addresses that make sense. The tool night build is available at the following url : http://sumo-test.irisa.fr:8080/DDS. A web service is also available that allow a request to the server to send an HL7 message to specific IP/port.
  • Add a dns entry to make it available under demographic-data-server.ihe.net .
  • Add entries for japan (firstname and lastname)
  • Write documentation for end user
  • Announce it, for trial usage
MIR Hand off design of PCC/CDA tests to Steve Moore Steve to start writing PCC/CDA content tests
MIR Have base classes for simulator actors, including command-line control program, WSDL web server control interface, server and client message processors, HL7V2 message server and client, simple HL7V2 client and server implementations Have tied together command line interface and WSDL applications. Need to tie in Web GUI


Planned Features (14-Sept-2009 thru 28-Sept-2009)

Who Projected Deliverable for 28-Sep-2009 Next Step
INRIA    
MIR - Miss from last time, need to deliver for 28-Sep At least one simulator/server responding to V3 queries (QED, or PIXV3, or PDQV3). Answers read out of a fixed database with SQL entered by hand (e.g., 5 PIX patients in a database, no GUI to enter more patients). Move that into DMZ for participant testing in Oct
MIR Web GUI that allows user to enter demographics and send V2 A04 message. The purpose is to place this tool in the MIR DMZ so users can send A04 messages with patient identifiers to the NIST registry, to registries from other participants and to PIX managers / PDQ suppliers available on the Internet. Need to tie Web GUI to Web Service functions.
MIR Start writing PCC content tests  
MIR Continue work on existing MESA platform for new profiles Oct 1 delivery data for participants

31-Aug-2009

Delivered Features (17-Aug-2009 thru 31-Aug-2009)

Who Delivered Next Step
INRIA Release of ProductRegistry Version 1.0-GA Announce it to vendor for data entry
MIR Finish investigation of PCC/CDA test content Hand off meeting 3-Sep. Work is complete
MIR Have base classes for simulator actors, including command-line control program, WSDL web server control interface, server and client message processors, HL7V2 message server and client, simple HL7V2 client and server implementations Base classes are done.
MIR Bring Kudu NA 2010 online. Finish testing data entry/registration pieces Open for registration.


Planned Features (1-Sept-2009 thru 14-Sept-2009)

Who Projected Deliverable for 14-Sep-2009 Next Step
INRIA Add Synchronization of GMM to TM and PR : We need to have a mechanism to automatically broadcast changes in the Master Model to propagate changes in the models toward slave applications  
INRIA Certificates management  
INRIA Objects management  
INRIA Migration to Jboss 5 and Java 6  
MIR At least one simulator/server responding to V3 queries (QED, or PIXV3, or PDQV3). Answers read out of a fixed database with SQL entered by hand (e.g., 5 PIX patients in a database, no GUI to enter more patients). Move that into DMZ for participant testing in Oct
MIR Web GUI that allows user to enter demographics and send V2 A04 message. The purpose is to place this tool in the MIR DMZ so users can send A04 messages with patient identifiers to the NIST registry, to registries from other participants and to PIX managers / PDQ suppliers available on the Internet. Synchronize with INRIA demographics service. Move to DMZ for Oct testing
MIR Start writing PCC content tests (MESA)  
MIR Continue work on existing MESA platform for new profiles Oct 1 delivery data for participants

17-Aug-2009

Delivered Features (3-Aug-2009 thru 17-Aug-2009)

Who Delivered Next Step
MIR (Maffitt/Kelsey) 1 week vacation  
INRIA (Poiseau) 2 week vacation  
MIR Investigate tooling to test content of PCC/CDA documents Finish investigation. Hand off to Steve
MIR Design basic structure for simulators / controllers Review NIST simulators
MIR Gazelle Master Model maintenance (bug fixes, no new features) Bug fixes as necessary

Planned Features (17-Aug-2009 thru 31-Aug-2009)

Who Projected Deliverable for 31-Aug-2009 Next Step
MIR Finish investigation of PCC/CDA test content Hand off to Steve by 31-Aug
MIR Have base classes for simulator actors, including command-line control program, WSDL web server control interface, server and client message processors, HL7V2 message server and client, simple HL7V2 client and server implementations Simulators
MIR Bring Kudu NA 2010 online. Finish testing data entry/registration pieces Open registration, 28-Aug-2009
INRIA Connectathon Monitor Management :
INRIA Configuration Management :
  • Added management of OID's to be used by test participants
  • Redesigned configuration for webservices as we have different types of webservices needs (RID, XDS a and b, HL7 V3 ...)
  • Added procedure to check list of possibles configuration for each actor/profile combination. This generates a report that helps the connectathon management team to check for missing configurations in the tool.
Check for missing configuration in the tool
INRIA Created a version of Gazelle for demonstration purpose. Available at the URL : http://sumo-test.irisa.fr:8080/gazelle-demo Add a dns entry to make it available under gazelle-demo.ihe.net and announce it.
INRIA Added the possibility to start tests and grade tests. User can select test partners, test is started and test engine is invoked for handling the "choreography" of the test.
  • Test engine and Gazelle Control Module do not share user : Fix it
  • Improve communication between Test Engine and Gazelle Control Module (requires migration to Jboss5)