Incomplete Missing MESA Software
From IHEWiki
[edit]
Introduction
This page documents that status of test development for Integration Profiles with no pre-connectathon tests assigned.
[edit]
Connectathon Participant Responsibilities
- For Pre-Connectathon (MESA) tests that are defined in Kudu and have implementations that are ready within one month of registration
- You need to complete the tests and enter the results by the deadlines as directed.
- If you find bugs/errors in the test plans or implementations, you need to log a bug report so the tests can be repaired.
- For Pre-Connectathon (MESA) tests that are delivered 30 days or more after the close of registration:
- We highly recommend that you run the tests and document the results.
- We understand that this is a burden and that you have other responsibilities. No organization will be penalized for not completing tests that are delivered late.
- You might find some of these same tests run at the Connectathon, so please do not ignore them.
- Internet Tests
- For some profiles with missing/incomplete software, we will encourage you to test with your partners over the Internet in advance of the Connectathon. We will facilitate where possible.
[edit]
Incomplete/Missing MESA Tests
This is the list of Pre-Connectathon tests that are missing or incomplete. This is organized by Domain. If you disagree with this assessment (profile Y is incomplete), send a note to Steve Moore. We are trying to disclose all known defects.
| Domain | Profile | Date | Status |
|---|---|---|---|
| AP | ARPH | 2009.10.30 | Active development, but tests are not ready. Do not have an ETA. |
| ITI | ATNA | 2009.10.30 | All existing logging tests are broken by CP 417. All existing TLS certificate tests are broken by the move to signed certificates.
|
| ITI | DSUB | 2009.10.30 | Active development, but tests are not ready. Do not have an ETA. |
| ITI | EUA | 2009.10.30 | No tests available. No active development. Perform Internet testing. |
| ITI | NAV | 2009.10.30 | No tests available. No estimate for delivery. Perform Internet testing. |
| ITI | PDQ-V3 | 2009.10.30 | Active development on updated tools, but tests are not ready. Do not have an ETA. |
| ITI | PIX-V3 | 2009.10.30 | Active development on updated tools, but tests are not ready. Do not have an ETA. |
| ITI | PSA | 2009.10.30 | No tests available. No active development. Perform Internet testing. |
| ITI | PWP | 2009.10.30 | Poor PWP tests. Skip these. |
| ITI | SVS | 2009.10.30 | No tests available. No active development. |
| ITI | XCPD | 2009.10.30 | No tests available. No active development. |
| PCC | APS | 2009.10.30 | Active development, but tests are not ready. Do not have an ETA. |
| PCC | APE | 2009.10.30 | Active development, but tests are not ready. Do not have an ETA. |
| PCC | APL | 2009.10.30 | Active development, but tests are not ready. Do not have an ETA. |
| PCC | CM | 2009.10.30 | No tests available. No active development. Perform Internet testing. |
| PCC | LDHP | 2009.10.30 | Active development, but tests are not ready. Do not have an ETA. |
| PCC | LDS | 2009.10.30 | Active development, but tests are not ready. Do not have an ETA. |
| PCC | MDS | 2009.10.30 | Active development, but tests are not ready. Do not have an ETA. |
| PCC | QED | 2009.10.30 | Active development, but tests are not ready. Do not have an ETA. |
| PCC | IC | 2009.10.30 | Active development, but tests are not ready. Do not have an ETA. |
| PCC | ETC | 2009.10.30 | Active development, but tests are not ready. Do not have an ETA. |
| PCC | PPOC | 2009.10.30 | Active development, but tests are not ready. Do not have an ETA. |
| QRPH | MCH | 2009.10.30 | No tests available. No active development. Perform Internet testing. |
| QRPH | CRD | 2009.10.30 | No tests available. No active development. Perform Internet testing. |
| QRPH | RPE | 2009.10.30 | No tests available. No active development. Perform Internet testing. |
| QRPH | DSC | 2009.10.30 | No tests available. No active development. Perform Internet testing. |
| RAD | BIR - Basic Image Review | 2009.10.30 | Image Set for BIR testing under active development. Connectathon test plan is under review. |
| RAD | PDI Extensions in Trial Implementation | 2009.10.30 | No tests available. No estimate for delivery. |
| RAD | PWF | 2009.10.30 | There are tests, but they are broken. Do not perform them. |
| RAD | XDS-I.b | 2009.10.30 | No tests available. No active development. Perform Internet testing. |